INTERSTATE 90 JANE ADDAMS MEMORIAL TOLLWAY

KANE AND COOK COUNTIES, ILLINOIS Phase 2 of the Jane Addams Memorial Tollway (I90) rebuilding and widening project focuses on a 25-mile segment throughout the eastern segment between Elgin Toll Plaza and the Kennedy Expressway. Gonzalez staff is providing Resident Engineer, Document Technician and construction inspection services for this work. Individual projects include:

Fiber Optic Relocation: Relocation of 22 miles of fiber optic cable. Aerial installation on wood poles includes conduit, fiber, and hand holes.

Bartlett Road Bridge: Removal and reconstruction of Bartlett Road bridge including retaining wall construction, drainage improvements, guardrail and concrete barrier, pavement marking, signage, lighting, earth excavation, grading, and maintenance of traffic.

Ramp Plaza Modifications: Modifications to three Tollway plazas including prefabricated plaza remote y p g p p building construction, lighting and electrical improvements, maintenance of traffic, and restoration of landscaping.

Des Plaines Oasis Bridge Demolition and Grading: Removal of Oasis structure, site grading, topsoil excavation and placement, drainage improvements, lighting removal and installation, and reconstruction of both eastbound and westbound oasis truck parking lots with Roller Compacted Concrete (RCC).

Advance ITS Relocation: Removal of existing and installation of temporary CCTV cameras, removal of existing RTMS units, re-aiming MVDS units, and relocation of existing DMS.

Genoa Road Interchange: Rehabilitation and widening of Genoa Road, including reconstruction of Ramps A and B, and removal of ram bridge over I-90. Installation of signage, pavement marking, guardrail, lighting, and new toll equipment.

I-39 ITS Fiber Optics Extension and Dynamic Message Sign: Installation of dynamic message sign on northbound I-39, and fiber optic cable along I90, including duct, hand holes, and cable. Installation of drainage structures, storm sewer, and erosion control.

Wetland Mitigation Orland Grasslands: Demolition of existing farmhouse buildings, removal of drain tiles, wetlands restoration, and pedestrian bridge.